US Construction Project Grounds to a Halt as Trump Defunds Hudson River Tunnels
In a move that's sent shockwaves through the construction industry, US President Donald Trump has ordered the withholding of funding for one of America's largest infrastructure projects - the $16 billion Gateway Development Commission. The project aimed to build new rail tunnels under the Hudson River but with federal grants and loans now on hold, officials have been left with no choice but to shut down operations.
According to Gateway CEO Tom Prendergast, "Today is a setback." The organization has exhausted all avenues to prevent an interruption to construction and now faces an uncertain future. The halt in work won't be as simple as turning off the lights - nearly a year of labor and $15 million to $20 million per month will be needed to wind down operations.
The Gateway Development Commission had already faced significant challenges, including a lawsuit filed by officials demanding $205 million in federal payments that have been withheld over the past four months. New York and New Jersey followed suit with their own lawsuits, seeking to force the money to flow.
However, it's not just the project itself that poses problems; shutting down the work will require significant resources to close up shop. Five job sites on either side of the Hudson River need to be backfilled, fences built around them, and security guards hired to prevent trespassers and vandals. Sections of the West Side Highway in Manhattan, which were dug up as part of the project, must also be restored, along with a bike lane that was rerouted.
Additionally, a significant portion of the Hudson River's bed, frozen and hardened with concrete to support the new tunnels, needs to be converted back to its original state. The massive cofferdam set up in the middle of the river to install this concrete must also be restored, requiring around-the-clock maintenance. Not to mention two massive boring machines that were ordered to carve out a 2.4-mile tunnel - these will need to be mothballed.
Gateway officials are already anticipating significant costs for maintaining all the project's sites while no construction takes place. The cost is expected to run $15 million to $20 million per month, according to lawyers with Gateway.
The move comes as a blow to the Gateway Development Commission, which had planned to eventually order two more boring machines for soft rock in the river bed. Project leaders are now facing an uncertain future, and experts warn that if the shutdown continues for too long, it won't be easy to get work started again.
In a move that's sent shockwaves through the construction industry, US President Donald Trump has ordered the withholding of funding for one of America's largest infrastructure projects - the $16 billion Gateway Development Commission. The project aimed to build new rail tunnels under the Hudson River but with federal grants and loans now on hold, officials have been left with no choice but to shut down operations.
According to Gateway CEO Tom Prendergast, "Today is a setback." The organization has exhausted all avenues to prevent an interruption to construction and now faces an uncertain future. The halt in work won't be as simple as turning off the lights - nearly a year of labor and $15 million to $20 million per month will be needed to wind down operations.
The Gateway Development Commission had already faced significant challenges, including a lawsuit filed by officials demanding $205 million in federal payments that have been withheld over the past four months. New York and New Jersey followed suit with their own lawsuits, seeking to force the money to flow.
However, it's not just the project itself that poses problems; shutting down the work will require significant resources to close up shop. Five job sites on either side of the Hudson River need to be backfilled, fences built around them, and security guards hired to prevent trespassers and vandals. Sections of the West Side Highway in Manhattan, which were dug up as part of the project, must also be restored, along with a bike lane that was rerouted.
Additionally, a significant portion of the Hudson River's bed, frozen and hardened with concrete to support the new tunnels, needs to be converted back to its original state. The massive cofferdam set up in the middle of the river to install this concrete must also be restored, requiring around-the-clock maintenance. Not to mention two massive boring machines that were ordered to carve out a 2.4-mile tunnel - these will need to be mothballed.
Gateway officials are already anticipating significant costs for maintaining all the project's sites while no construction takes place. The cost is expected to run $15 million to $20 million per month, according to lawyers with Gateway.
The move comes as a blow to the Gateway Development Commission, which had planned to eventually order two more boring machines for soft rock in the river bed. Project leaders are now facing an uncertain future, and experts warn that if the shutdown continues for too long, it won't be easy to get work started again.